# Create Task Link

POST https://api.projectmanager.com/api/data/tasks/{taskId}/links-to
Content-Type: application/json

Creates a new link (dependency) from this Task to another Task in the same Project.
            
A Task Link connects a predecessor Task to a successor Task, indicating a scheduling
dependency between them. The link type controls how the two Tasks' dates relate to
each other, and lag adds (or, if negative, removes) time between them.
            
Valid LinkType values (case-insensitive): finishToStart, startToStart, finishToFinish, startToFinish.
Omitting LinkType defaults to finishToStart.

Reference: https://developer.projectmanager.com/api-reference/task-link/create-task-link

## Authentication

- `Authorization` header (bearer token, required) — Bearer authentication of the form `Bearer <token>`, where token is your auth token.

## Request

### Path parameters

- `taskId` (string, required) — The unique identifier of the predecessor Task for this link

### Headers

- `x-integration-name` (string, optional) — The name of the calling system passed along as a header parameter

### Body (application/json)

This endpoint expects a TaskLinkCreateDto.

- `successorTaskId` (string, optional) — The unique identifier of the successor Task to link to. This Task must be in the same Project as the predecessor Task the link is being created from.
- `linkType` (string, optional) — The type of dependency between the two Tasks. Case-insensitive; stored and returned in camelCase. Valid values: finishToStart, startToStart, finishToFinish, startToFinish. Defaults to finishToStart when omitted.
- `lag` (integer, optional) — The number of days of lag (or lead, if negative) between the two Tasks.

## Response

### 200

Success

- `error` (AstroError, optional, nullable) — If the API call failed, this will contain information about the error that occurred.
- `success` (boolean, optional) — True if the API call succeeded; false otherwise.
- `hasError` (boolean, optional) — True if the API call failed.
- `statusCode` (enum, optional) — The HTTP code of the response.
  - Allowed values: `Continue`, `SwitchingProtocols`, `Processing`, `EarlyHints`, `OK`, `Created`, `Accepted`, `NonAuthoritativeInformation`, `NoContent`, `ResetContent`, `PartialContent`, `MultiStatus`, `AlreadyReported`, `IMUsed`, `MultipleChoices`, `MovedPermanently`, `Found`, `SeeOther`, `NotModified`, `UseProxy`, `Unused`, `TemporaryRedirect`, `PermanentRedirect`, `BadRequest`, `Unauthorized`, `PaymentRequired`, `Forbidden`, `NotFound`, `MethodNotAllowed`, `NotAcceptable`, `ProxyAuthenticationRequired`, `RequestTimeout`, `Conflict`, `Gone`, `LengthRequired`, `PreconditionFailed`, `RequestEntityTooLarge`, `RequestUriTooLong`, `UnsupportedMediaType`, `RequestedRangeNotSatisfiable`, `ExpectationFailed`, `MisdirectedRequest`, `UnprocessableEntity`, `Locked`, `FailedDependency`, `UpgradeRequired`, `PreconditionRequired`, `TooManyRequests`, `RequestHeaderFieldsTooLarge`, `UnavailableForLegalReasons`, `InternalServerError`, `NotImplemented`, `BadGateway`, `ServiceUnavailable`, `GatewayTimeout`, `HttpVersionNotSupported`, `VariantAlsoNegotiates`, `InsufficientStorage`, `LoopDetected`, `NotExtended`, `NetworkAuthenticationRequired`
- `data` (ChangeSetStatusDto, optional) — Returns the id of a specific ChangeSet

## Types

### AstroError

Information about an error that occurred within the ProjectManager API.

- `technicalError` (string, optional, nullable) — A technical description of the error that occurred. Not suitable for display to end users.
- `additionalErrors` (list of string, optional, nullable) — If additional errors beyond the main error in `Message` occurred, they will be listed here as individual messages.
- `validationErrors` (map from string to list of string, optional, nullable) — This contains a dictionary of validation errors. The key is the name of the field
- `message` (string, optional, nullable) — A description of the error that occurred. If your application has a user interface, show this message to explain what went wrong.

### ChangeSetStatusDto

Returns the id of a specific ChangeSet

- `changeSetId` (string, optional) — The unique identifier of this Changeset
- `id` (string, optional) — The unique identifier of the entity affected by this Changeset. For example, if this Changeset was created for a Task, this value will be the unique identifier for the Task.

## Examples

**Request**

```json
{}
```

**Response**

```json
{
  "error": {
    "technicalError": "string",
    "additionalErrors": [
      "string"
    ],
    "validationErrors": {},
    "message": "string"
  },
  "success": true,
  "hasError": true,
  "statusCode": "Continue",
  "data": {
    "changeSetId": "string",
    "id": "string"
  }
}
```

**SDK Code**

```python
import requests

url = "https://api.projectmanager.com/api/data/tasks/taskId/links-to"

payload = {}
headers = {
    "Authorization": "Bearer <token>",
    "Content-Type": "application/json"
}

response = requests.post(url, json=payload, headers=headers)

print(response.json())
```

```javascript
const url = 'https://api.projectmanager.com/api/data/tasks/taskId/links-to';
const options = {
  method: 'POST',
  headers: {Authorization: 'Bearer <token>', 'Content-Type': 'application/json'},
  body: '{}'
};

try {
  const response = await fetch(url, options);
  const data = await response.json();
  console.log(data);
} catch (error) {
  console.error(error);
}
```

```go
package main

import (
	"fmt"
	"strings"
	"net/http"
	"io"
)

func main() {

	url := "https://api.projectmanager.com/api/data/tasks/taskId/links-to"

	payload := strings.NewReader("{}")

	req, _ := http.NewRequest("POST", url, payload)

	req.Header.Add("Authorization", "Bearer <token>")
	req.Header.Add("Content-Type", "application/json")

	res, _ := http.DefaultClient.Do(req)

	defer res.Body.Close()
	body, _ := io.ReadAll(res.Body)

	fmt.Println(res)
	fmt.Println(string(body))

}
```

```ruby
require 'uri'
require 'net/http'

url = URI("https://api.projectmanager.com/api/data/tasks/taskId/links-to")

http = Net::HTTP.new(url.host, url.port)
http.use_ssl = true

request = Net::HTTP::Post.new(url)
request["Authorization"] = 'Bearer <token>'
request["Content-Type"] = 'application/json'
request.body = "{}"

response = http.request(request)
puts response.read_body
```

```java
import com.mashape.unirest.http.HttpResponse;
import com.mashape.unirest.http.Unirest;

HttpResponse<String> response = Unirest.post("https://api.projectmanager.com/api/data/tasks/taskId/links-to")
  .header("Authorization", "Bearer <token>")
  .header("Content-Type", "application/json")
  .body("{}")
  .asString();
```

```php
<?php
require_once('vendor/autoload.php');

$client = new \GuzzleHttp\Client();

$response = $client->request('POST', 'https://api.projectmanager.com/api/data/tasks/taskId/links-to', [
  'body' => '{}',
  'headers' => [
    'Authorization' => 'Bearer <token>',
    'Content-Type' => 'application/json',
  ],
]);

echo $response->getBody();
```

```csharp
using RestSharp;

var client = new RestClient("https://api.projectmanager.com/api/data/tasks/taskId/links-to");
var request = new RestRequest(Method.POST);
request.AddHeader("Authorization", "Bearer <token>");
request.AddHeader("Content-Type", "application/json");
request.AddParameter("application/json", "{}", ParameterType.RequestBody);
IRestResponse response = client.Execute(request);
```

```swift
import Foundation

let headers = [
  "Authorization": "Bearer <token>",
  "Content-Type": "application/json"
]
let parameters = [] as [String : Any]

let postData = JSONSerialization.data(withJSONObject: parameters, options: [])

let request = NSMutableURLRequest(url: NSURL(string: "https://api.projectmanager.com/api/data/tasks/taskId/links-to")! as URL,
                                        cachePolicy: .useProtocolCachePolicy,
                                    timeoutInterval: 10.0)
request.httpMethod = "POST"
request.allHTTPHeaderFields = headers
request.httpBody = postData as Data

let session = URLSession.shared
let dataTask = session.dataTask(with: request as URLRequest, completionHandler: { (data, response, error) -> Void in
  if (error != nil) {
    print(error as Any)
  } else {
    let httpResponse = response as? HTTPURLResponse
    print(httpResponse)
  }
})

dataTask.resume()
```